Winlow Place Street Repaving

Two Phases: Hazard St Paved — Side Streets Up Next

Update, November 18:

  • Hazard St has been repaved, ahead of the December 3 finish date. Its three asphalt speed cushions go in November 23–27.

  • Phase 2 on the side streets:

    • Could start as early as Saturday, November 21, but that isn’t guaranteed. The more likely start is Lanier’s Thanksgiving break, November 23–27.

    • If you live on Hawthorne, Harold, Kipling or Marshall, watch for door tags and No Parking signs.

    • Existing speed humps on the side streets will be replaced with speed cushions too.

  • The crosswalks and stop lines will be repainted.


After years on the City’s Capital Improvement Plan and months on hold behind the Montrose water line project, Houston Public Works (HPW) is repaving Winlow Place streets. The work will happen in two phases:

  • Phase 1 – Hazard St: paved; speed cushions November 23–27

  • Phase 2 – Asphalt side streets: as early as November 21; expected November 23–27

Winlow Place repaving status, November 18: Hazard St paved, speed cushions November 23–27, and Phase 2 on Hawthorne, Harold, Kipling and Marshall possibly starting November 21 and expected November 23–27.

Winlow Place repaving status on November 18: Hazard St is paved; speed cushions and the Phase 2 side streets (orange) are next. Schematic, not to scale.

Phase 1: HAZARD ST (PAVED)

Where: Hazard St, from Westheimer to W Alabama, along Lanier Middle School

When: Started Wednesday, November 4. Paving was complete by November 18, ahead of the scheduled December 3 finish.

Work: Mill and overlay, which means grinding off the old asphalt and laying a new surface.

Speed cushions: The 3 existing full-width speed humps on Hazard will be replaced with asphalt speed cushions, built to the City's standard design:

  • Raised sections with white chevrons and gaps between them, so emergency vehicles can pass through while cars still slow down.

  • Final locations are set by the City.

  • They go in November 23–27.

Crosswalks and stop lines: The contractor has confirmed that the painted crosswalks and the stop lines at stop signs will be repainted after paving. On Hazard, crosswalks cross the south side of Westheimer and all four sides of the Harold intersection by Lanier. We photographed them before paving so we can check they all come back.

Lanier Middle School: The school has been notified, and the principal will let parents know about traffic changes.

Contractor: JFT Construction, Inc. The contractor and HPW walked Hazard St on October 29–30 to price the work.

Phase 2: ASPHALT SIDE STREETS (STARTING AS EARLY AS NOVEMBER 21)

Where: The asphalt side streets shown in orange on the map above. The contractor’s own location map shows the same four streets:

  • Hawthorne St: McDuffie to Hazard

  • Harold St: McDuffie to Dunlavy

  • Kipling St: McDuffie to Woodhead

  • Marshall St: McDuffie to Dunlavy

When: The contractor says there’s a chance work starts Saturday, November 21. The more likely start is during Lanier Middle School’s Thanksgiving break, November 23–27, when school traffic is light. You should get a door tag before work begins on your block.

Work: Full mill and overlay.

Speed cushions: The existing speed humps on these streets will also be replaced with asphalt speed cushions, the same design as on Hazard.

Oversight: A City inspector or HPW project manager will be on site.

Sources: contractor update and Phase 2 location map, November 18.


Today’s full-width speed hump vs. new speed cushions: three raised sections with gaps that fire trucks can straddle.

Today’s full-width speed hump compared with the asphalt speed cushions replacing them on Hazard St and the side streets. Illustration, not to scale.


What's Not Included

Streets west of McDuffie (hatched area on the map): Dropped for now. Private development there will require more street cuts.

  • Curbs and gutters: The work covers the road surface only. It will not fix the curb and gutter problems that cause water to pond on some blocks.

  • Concrete streets: Only the asphalt streets marked on the map are part of this project.

What's next: HPW has told our neighbors at the WAMM Civic Association that the same east–west streets east of Dunlavy are scheduled after Winlow Place.

During Construction

Watch for "No Parking" signs and move vehicles off the street on work days.

  • Expect lane closures, flaggers and noise, and brief limits on driveway access while crews mill and pave.

  • Allow extra time around Lanier at school drop-off and pick-up.

Who to Contact

  • Emergencies (24 hours): JFT Construction, Ismael Hernandez, 832-274-1726

  • Non-emergencies and complaints: Call 311 or email buildforward@houstontx.gov

  • HPW Project Manager: Adrian Carter, 713-829-0260

  • Questions about this update: president@winlowplace.org

Help us check the finished work. Recent overlay jobs nearby were left uneven, and their lane striping, crosswalks and speed humps went unrestored for months. If a crosswalk, stop line or speed cushion is missing after the work is done, report it to 311 and note the service request number.

Thank You

Thank you to the office of District C Council Member Joe Panzarella, Rene Ruiz of the Mayor's Assistance Office (Department of Neighborhoods), Houston Public Works, the Neartown/Montrose Super Neighborhood, and Kevin and Chris Sokol-White of the WAMM Civic Association for helping get answers for our neighborhood.

We'll post updates as the work moves along.

Additional Files and images

Construction notice (door tag) from Houston Public Works, delivered on Hazard St, Oct 30, 2026 (PDF)

Full-size repaving map

Full-size speed cushion illustration

Previous
Previous

Winlow Place WhatsApp Community

Next
Next

Trees for Winlow Place